Redundancy in WinCC OA: hot standby, and when you need 2x2 disaster recovery

How hot standby works, what it protects against, and when a site needs 2x2 redundancy for disaster recovery.

4 min read

Start with the failure you need to survive

A discussion about redundancy should start with the operating requirement. Losing a manager is different from losing a server, a network path or an entire control centre. Putting another server in the design does not establish what operators will see or which failures the installation can tolerate.

We identify the functions that must remain available and the dependencies behind them. The review includes communications, operator access and historical data. We then describe the expected response to each failure. Those descriptions become test cases. Without them, an architecture diagram can look convincing while leaving important operating questions unanswered.

What a hot-standby pair does

WinCC OA redundancy uses an active server and a standby server that both run the project. Runtime data is synchronised between the pair. The redundancy configuration monitors system conditions and determines which server is active. Clients connect to the pair and use the active server’s data.

The changeover behaviour depends on the configured monitoring and error weighting. We review which manager failures or communication conditions should cause a switch. We also check driver-specific behaviour and the application’s use of active and passive roles. Hot standby is a system function, but the complete application still needs to be tested with it.

Look beyond the server pair

Two servers can still depend on the same power supply, network equipment or location. A server pair is not automatically protection against the loss of that shared dependency. We examine the installation as a whole, including how operators reach the system and how the system reaches the field.

There is also a distinction between redundancy and backup. A standby server is part of the running system. It does not remove the need for recoverable project files, configuration records and a tested restoration method. An incorrect application change can affect both members of a pair if it is introduced to both.

When the design needs a second centre

A 2x2 arrangement places a redundant pair at the primary centre and another pair at a recovery centre. The purpose is to address the loss of a complete primary system or location, not just the loss of one server. The second centre needs a defined operating role and the connections to carry it out.

WinCC OA’s documented Disaster Recovery System extends hot standby with a secondary system operating in warm standby. Synchronisation between centres has its own configuration and restrictions. A distributed-system connection alone does not establish a complete disaster-recovery arrangement. We review the supported version, interfaces and historical-data setup before selecting the implementation.

Two centres, two servers per centreA primary server system and a secondary recovery system each contain a hot-standby pair. Distributed-system connections and control logic link the centres. Normally the primary system handles field connections and sends process data to the secondary system.Primary centreServer AServer BHot-standby pairDIST + control logicRecovery centreServer CServer DHot-standby pair
Conceptual 2×2 layout. Separate tested operating rules for primary-centre loss and inter-centre communication loss.

Treat a broken link as its own case

Loss of inter-centre communications is not the same as proof that the primary centre has failed. The design needs an explicit response for that condition. We define how the system indicates uncertainty, which location may operate and how the sites return to normal after communications are restored.

We also identify which online values, alarm states, configuration and history need to be available at the recovery centre. Their update and recovery mechanisms are not assumed to be identical. The records should describe the limits of the tested arrangement so that operators do not infer more continuity than the installation provides.

Test recovery as an operating procedure

FAT should exercise the selected failure cases, not only a planned active-server switch. We test manager failures, loss of the active server and the communication conditions represented in the test environment. For a recovery-centre design, we include loss of the primary system and the return to normal service.

Site testing then checks the installed dependencies and operator access. We record what is visible during each transition, how commands are handled and what happens to the required historical information. Handover includes the recovery procedure and the tested limitations. The decision to use 2x2 follows those operating requirements, rather than a preference for a larger architecture.